Glentaggart WF 33kV: grid connection queue
Glentaggart WF 33kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 42 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2027 to 31 Oct 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Glentaggart 42MW BESS | GLENTAGGART WIND LIMITED | Battery storage | 42 | 31 Oct 2027 | High | 30 Oct 2029 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Douglas West | SP Energy Networks | 8.5 km | 22 MW | 15 MW |
| Symington | SP Energy Networks | 15.3 km | 12 MW | 3.3 MW |
| Lesmahagow | SP Energy Networks | 16.6 km | 10 MW | 15 MW |
| Corra Linn | SP Energy Networks | 16.8 km | 4.6 MW | 8 MW |
| Lanark | SP Energy Networks | 18.3 km | 26 MW | 17 MW |
| Fauldhead | SP Energy Networks | 19.5 km | 9.4 MW | 5.7 MW |
Thinking of connecting near Glentaggart WF 33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- GLENTAGGART 150MW BESS 132kV SUBSTATION: 150 MW waiting
- Red Moss Farm 132kV: 300 MW waiting
- Redshaw 132kV Substation.: 620 MW waiting
- Redshaw 400kV: 504 MW waiting
- Bodinglee Wind Farm 132kV: 280 MW waiting