Elvanfoot 400/275/33kV: grid connection queue
Elvanfoot 400/275/33kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 10 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2027 to 30 Apr 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Elvanfoot (9.8 MW) Energy Storage | ELVANFOOT ENERGY STORAGE LIMITED | Battery storage | 9.8 | 30 Apr 2027 | High | 29 Apr 2029 | Consents Approved | 2 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Douglas West | SP Energy Networks | 19.0 km | 22 MW | 15 MW |
| Symington | SP Energy Networks | 19.0 km | 12 MW | 3.3 MW |
| Moffat | SP Energy Networks | 19.5 km | 8.5 MW | 3.6 MW |
Thinking of connecting near Elvanfoot 400/275/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- ELVANFOOT ENERGY STORAGE 132/33KV COLLECTOR SUBSTATION: 75 MW waiting
- Elvanfoot substation: 44 MW waiting
- Rivox 132/33kV: 220 MW waiting
- Glenglass 132/33kV: 60 MW waiting
- Red Moss Farm 132kV: 300 MW waiting