CHALMERSTON WINDFARM 132kV SUBSTATION: grid connection queue
CHALMERSTON WINDFARM 132kV SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 75 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Chalmerston Windfarm | BROCKWELL ENERGY LIMITED | Onshore wind | 75 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Chalmerston Windfarm | 31 Oct 2033 | 31 Oct 2037 | +48 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Lethanhill | SP Energy Networks | 7.7 km | 25 MW | 14 MW |
| New Cumnock | SP Energy Networks | 10.3 km | -67 MW | 7.8 MW |
| Killoch Colliery | SP Energy Networks | 11.9 km | 27 MW | 8.3 MW |
| Cumnock | SP Energy Networks | 12.9 km | 14 MW | |
| Mauchline | SP Energy Networks | 17.8 km | 11 MW | 4.6 MW |
| Glengall | SP Energy Networks | 17.8 km | 24 MW | 9 MW |
Thinking of connecting near CHALMERSTON WINDFARM 132kV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Enoch Hill 2 Wind Farm 33kV: 10 MW waiting
- Dersalloch 132/33kV: 11 MW waiting
- Sclenteuch Energy Park 132kV: 54 MW waiting
- Benbrack Wind Farm 132/33kV: 42 MW waiting
- Coylton 275kV substation: 450 MW waiting