Boydston 400kV substation: grid connection queue
Boydston 400kV substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 350 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Nov 2026 to 30 Nov 2026.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Kilmarnock BESS | Kilmarnock Flexpower Ltd | Battery storage | 350 | 30 Nov 2026 | High | 29 Nov 2028 | Under Construction/Commissioning | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 30 Jun 2026 | Kilmarnock BESS | 31 Oct 2026 | 30 Nov 2026 | +1 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kilmarnock Main | SP Energy Networks | 4.7 km | 27 MW | 12 MW |
| Queens Drive | SP Energy Networks | 4.8 km | 15 MW | |
| Grassyards | SP Energy Networks | 5.5 km | 11 MW | |
| Langlands Street | SP Energy Networks | 6.0 km | 23 MW | 11 MW |
| Newmilns | SP Energy Networks | 7.3 km | 16 MW | |
| Mauchline | SP Energy Networks | 7.8 km | 11 MW | 4.6 MW |
Thinking of connecting near Boydston 400kV substation?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Kilmarnock South 400kV: 500 MW waiting
- Whitelee Extension 275/33kV: 89 MW waiting
- Kilmarnock Town 275/33kV: 60 MW waiting
- Killoch BESS 132kV: 150 MW waiting
- Kilwinning 132/33kV: 190 MW waiting