Benzene

Boydston 400kV substation: grid connection queue

Boydston 400kV substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 350 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Nov 2026 to 30 Nov 2026.

1project in the queue
350 MWwaiting to connect
0 MWalready connected
350 MWholding Gate 2
1date moves since 2 Jun 2026
350 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Kilmarnock BESSKilmarnock Flexpower LtdBattery storage35030 Nov 2026High29 Nov 2028Under Construction/Commissioning2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
30 Jun 2026Kilmarnock BESS31 Oct 202630 Nov 2026+1 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Kilmarnock MainSP Energy Networks4.7 km27 MW12 MW
Queens DriveSP Energy Networks4.8 km15 MW
GrassyardsSP Energy Networks5.5 km11 MW
Langlands StreetSP Energy Networks6.0 km23 MW11 MW
NewmilnsSP Energy Networks7.3 km16 MW
MauchlineSP Energy Networks7.8 km11 MW4.6 MW

Thinking of connecting near Boydston 400kV substation?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points