Kilwinning 132/33kV: grid connection queue

Kilwinning 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026

3 projects with 190 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 3 Apr 2025 to 27 Apr 2029.

3projects in the queue
190 MWwaiting to connect
0 MWalready connected
163 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Benthead SolarBENTHEAD SOLAR LIMITEDSolar + storage633 Apr 2025n/aConsents Approved2
Ardoch Farm Battery StorageCAPBAL (KILWINNING) LIMITEDBattery storage2730 Apr 2026n/aScopingnone
Flemyland Battery StorageFlemyland Battery Storage LimitedBattery storage10027 Apr 2029Medium27 Apr 2029Consents Approved2

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Dalrymple DriveSP Energy Networks0.5 km12 MW
IrvineSP Energy Networks1.2 km24 MW4.1 MW
RiversideSP Energy Networks2.0 km18 MW36 MW
RavensparkSP Energy Networks2.3 km13 MW
ByrehillSP Energy Networks5.4 km21 MW17 MW
StevenstonSP Energy Networks6.8 km11 MW7.5 MW

Thinking of connecting near Kilwinning 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points