Auchentiber Farm BESS 400kV: grid connection queue

Auchentiber Farm BESS 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 700 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 17 Oct 2029 to 17 Oct 2029.

1project in the queue
700 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Auchentiber Farm 700MW BESSGPC 700 LtdBattery storage70017 Oct 2029Medium17 Oct 2029Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
StewartonSP Energy Networks4.0 km6.3 MW
KilbirnieSP Energy Networks7.5 km12 MW
RavensparkSP Energy Networks8.7 km13 MW
ByrehillSP Energy Networks8.8 km21 MW17 MW
Dalrymple DriveSP Energy Networks9.0 km12 MW
RiversideSP Energy Networks10.4 km18 MW36 MW

Thinking of connecting near Auchentiber Farm BESS 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points