Neilston 400kV: grid connection queue

Neilston 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

2 projects with 1,000 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2029 to 31 Oct 2033.

2projects in the queue
1,000 MWwaiting to connect
0 MWalready connected
600 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Neilston 400kV Greener Grid ParkStatkraft UK LtdBattery storage60031 Oct 2029Medium31 Oct 2029Consents Approved2
Hurlet BatteryP-FREQUENCY LTDBattery storage40031 Oct 2033Low31 Oct 2033Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
18 Aug 2026Neilston 400kV Greener Grid Park17 May 202731 Oct 2029+30 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Aurs RoadSP Energy Networks3.5 km-3.3 MW14 MW
BarrheadSP Energy Networks3.7 km23 MW14 MW
GlenburnSP Energy Networks4.6 km11 MW4.2 MW
FoxbarSP Energy Networks5.3 km16 MW
BarterholmSP Energy Networks5.7 km24 MW11 MW
CrookstonSP Energy Networks5.8 km27 MW10 MW

Thinking of connecting near Neilston 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.