Neilston 400kV: grid connection queue
Neilston 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 1,000 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2029 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Neilston 400kV Greener Grid Park | Statkraft UK Ltd | Battery storage | 600 | 31 Oct 2029 | Medium | 31 Oct 2029 | Consents Approved | 2 |
| Hurlet Battery | P-FREQUENCY LTD | Battery storage | 400 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 18 Aug 2026 | Neilston 400kV Greener Grid Park | 17 May 2027 | 31 Oct 2029 | +30 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Aurs Road | SP Energy Networks | 3.5 km | -3.3 MW | 14 MW |
| Barrhead | SP Energy Networks | 3.7 km | 23 MW | 14 MW |
| Glenburn | SP Energy Networks | 4.6 km | 11 MW | 4.2 MW |
| Foxbar | SP Energy Networks | 5.3 km | 16 MW | |
| Barterholm | SP Energy Networks | 5.7 km | 24 MW | 11 MW |
| Crookston | SP Energy Networks | 5.8 km | 27 MW | 10 MW |
Thinking of connecting near Neilston 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Elderslie 132/33kV: 89 MW waiting
- Paisley: 60 MW waiting
- MIDDLETON FARM 400KV SUBSTATION: 937 MW waiting
- Linwood 400kV: 400 MW waiting
- Giffnock 275/33kV: 40 MW waiting