Elderslie 132/33kV: grid connection queue
Elderslie 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 89 MW are waiting to connect here (largest by capacity: battery storage, solar). Contracted dates run from 28 Jun 2028 to 28 Jun 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Well Street Paisley | Gas Generation Property Limited | Battery storage | 50 | 28 Jun 2028 | High | 28 Jun 2030 | Consents Approved | 2 |
| Middleton Farm Solar | Bluestone Middleton Farm 1 Ltd | Solar | 39 | 28 Jun 2028 | High | 13 Jul 2030 | Scoping | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 28 Jul 2026 | Middleton Farm Solar | 6 Oct 2025 | 28 Jun 2028 | +33 months |
| 23 Jun 2026 | Well Street Paisley | 6 May 2025 | 28 Jun 2028 | +38 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Foxbar | SP Energy Networks | 0.6 km | 16 MW | |
| Glenburn | SP Energy Networks | 1.3 km | 11 MW | 4.2 MW |
| Barterholm | SP Energy Networks | 2.3 km | 24 MW | 11 MW |
| Underwood | SP Energy Networks | 2.4 km | 21 MW | 4.2 MW |
| Blackhall Package | SP Energy Networks | 2.7 km | 18 MW | |
| Johnstone (Primary) | SP Energy Networks | 3.3 km | 23 MW | 11 MW |
Thinking of connecting near Elderslie 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Paisley: 60 MW waiting
- MIDDLETON FARM 400KV SUBSTATION: 937 MW waiting
- Linwood 400kV: 400 MW waiting
- Neilston 400kV: 1,000 MW waiting
- Braehead Park 132/33kV: 100 MW waiting