Paisley: grid connection queue
Paisley GSP · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 60 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 1 Oct 2028 to 1 Oct 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Stanley Water WTW BESS | Bluestone Energy Ltd | Battery storage | 60 | 1 Oct 2028 | High | 1 Oct 2030 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Underwood | SP Energy Networks | 0.6 km | 21 MW | 4.2 MW |
| Blackhall Package | SP Energy Networks | 0.8 km | 18 MW | |
| Sherwood | SP Energy Networks | 1.0 km | 23 MW | 16 MW |
| Barterholm | SP Energy Networks | 1.3 km | 24 MW | 11 MW |
| Glasgow Airport | SP Energy Networks | 2.1 km | 18 MW | 11 MW |
| Glenburn | SP Energy Networks | 2.6 km | 11 MW | 4.2 MW |
Thinking of connecting near Paisley?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Elderslie 132/33kV: 89 MW waiting
- MIDDLETON FARM 400KV SUBSTATION: 937 MW waiting
- Braehead Park 132/33kV: 100 MW waiting
- Linwood 400kV: 400 MW waiting
- Partrick: 63 MW waiting