Linwood 400kV: grid connection queue
Linwood 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 400 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 28 Oct 2033 to 28 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Lightsource Auchans | Lightsource Renewable UK Development Limited | Battery storage | 400 | 28 Oct 2033 | Low | 28 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Ardgour Drive | SP Energy Networks | 1.6 km | 23 MW | 7 MW |
| Johnstone (Primary) | SP Energy Networks | 2.2 km | 23 MW | 11 MW |
| Glasgow Airport | SP Energy Networks | 2.9 km | 18 MW | 11 MW |
| Underwood | SP Energy Networks | 3.3 km | 21 MW | 4.2 MW |
| Foxbar | SP Energy Networks | 3.3 km | 16 MW | |
| Milliken | SP Energy Networks | 4.3 km | 23 MW | 13 MW |
Thinking of connecting near Linwood 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- MIDDLETON FARM 400KV SUBSTATION: 937 MW waiting
- Elderslie 132/33kV: 89 MW waiting
- Paisley: 60 MW waiting
- Braehead Park 132/33kV: 100 MW waiting
- Vale of Leven 132kV substation: 72 MW waiting