Vale of Leven 132kV substation: grid connection queue

Vale of Leven 132kV substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 72 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.

1project in the queue
72 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Vale of Leven Wind FarmVale of Leven Wind Farm LimitedOnshore wind7231 Oct 2033Low31 Oct 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
ErskineSP Energy Networks2.3 km21 MW
KilbowieSP Energy Networks2.7 km22 MW12 MW
Radnor ParkSP Energy Networks3.1 km22 MW14 MW
Clydebank Business ParkSP Energy Networks3.3 km12 MW
Abbeylands RoadSP Energy Networks3.8 km11 MW7.7 MW
Hecla AvenueSP Energy Networks5.1 km22 MW16 MW

Thinking of connecting near Vale of Leven 132kV substation?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.