Windyhill 132kV: grid connection queue
Windyhill 132kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Dec 2027 to 31 Dec 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| WindyHill Energy Storage Facility | Windyhill Grid 1 LTD | Battery storage | 200 | 31 Dec 2027 | High | 30 Dec 2029 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 30 Jun 2026 | WindyHill Energy Storage Facility | 27 Aug 2025 | 31 Dec 2027 | +28 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Abbeylands Road | SP Energy Networks | 1.3 km | 11 MW | 7.7 MW |
| Hecla Avenue | SP Energy Networks | 2.1 km | 22 MW | 16 MW |
| Craigdhu Road | SP Energy Networks | 2.5 km | 16 MW | |
| Kilbowie | SP Energy Networks | 2.7 km | 22 MW | 12 MW |
| Drumchapel Road | SP Energy Networks | 2.8 km | 23 MW | 14 MW |
| Radnor Park | SP Energy Networks | 2.8 km | 22 MW | 14 MW |
Thinking of connecting near Windyhill 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Braidfield Battery Storage 132kV: 100 MW waiting
- Drumchapel 275/33kV: 60 MW waiting
- Vale of Leven 132kV substation: 72 MW waiting
- Partrick: 63 MW waiting
- Braehead Park 132/33kV: 100 MW waiting