Giffnock 275/33kV: grid connection queue

Giffnock 275/33kV · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 40 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2028.

1project in the queue
40 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
40 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Glasgow Road 40MW BESSGPC 1137 LtdBattery storage4031 Oct 2028High31 Oct 2030Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
CastleSP Energy Networks3.9 km2.6 MW2.5 MW
JacktonSP Energy Networks4.0 km22 MW19 MW
ClarkstonSP Energy Networks5.5 km27 MW11 MW
Berryhill RoadSP Energy Networks6.3 km23 MW12 MW
WestwoodSP Energy Networks6.5 km17 MW
College MiltonSP Energy Networks6.6 km19 MW8.4 MW

Thinking of connecting near Giffnock 275/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points