Castlemilk 400kV: grid connection queue
Castlemilk 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 300 MW is waiting to connect here (largest by capacity: solar). Contracted dates run from 31 Oct 2036 to 31 Oct 2036.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Castlemilk 1 | Queequeg Renewables Ltd | Solar | 300 | 31 Oct 2036 | Low | 31 Oct 2036 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Castlemilk | SP Energy Networks | 2.1 km | 20 MW | 15 MW |
| Markethill | SP Energy Networks | 2.8 km | 27 MW | 13 MW |
| Whitlawburn | SP Energy Networks | 2.9 km | 22 MW | |
| College Milton | SP Energy Networks | 3.2 km | 19 MW | 8.4 MW |
| Westfield Ave | SP Energy Networks | 3.5 km | 23 MW | 11 MW |
| Carmunnock Road | SP Energy Networks | 3.7 km | 26 MW | 15 MW |
Thinking of connecting near Castlemilk 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Busby 275kV: 150 MW waiting
- Clydesmill 275/33kV: 363 MW waiting
- Clydesmill: 40 MW waiting
- Dalmarnock Storage BESS 132kV: 192 MW waiting
- DALMARNOCK 132/33KV SUBSTATION: 40 MW waiting