Dalmarnock Storage BESS 132kV: grid connection queue
Dalmarnock Storage BESS 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 192 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2028 to 30 Apr 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Downiebrae BESS | DOWNIEBRAE BESS LTD | Battery storage | 150 | 30 Apr 2028 | High | 30 Apr 2030 | Scoping | 1 |
| Dalmarnock Storage BESS | VIRIDISIA LTD | Battery storage | 42 | 30 Apr 2030 | Medium | 30 Apr 2030 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Ashgrove Street | SP Energy Networks | 0.7 km | 23 MW | 8 MW |
| Maukinfauld Road | SP Energy Networks | 1.1 km | 20 MW | |
| David Street | SP Energy Networks | 1.4 km | 22 MW | 10 MW |
| Eckford Street | SP Energy Networks | 2.1 km | 20 MW | 9.9 MW |
| Eastercraigs | SP Energy Networks | 2.3 km | 23 MW | 9.4 MW |
| Cambuslang | SP Energy Networks | 2.4 km | 18 MW |
Thinking of connecting near Dalmarnock Storage BESS 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- DALMARNOCK 132/33KV SUBSTATION: 40 MW waiting
- Carntyne (SPD): 50 MW waiting
- Clydesmill 275/33kV: 363 MW waiting
- Clydesmill: 40 MW waiting
- Whitehill Bess 275/132kV: 500 MW waiting