Clydesmill: grid connection queue
Clydesmill GSP · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 40 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2029 to 30 Apr 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Gilbertfield Farm BESS | GPC 678 LTD | Battery storage | 40 | 30 Apr 2029 | Medium | 30 Apr 2029 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Cambuslang | SP Energy Networks | 1.2 km | 18 MW | |
| Eckford Street | SP Energy Networks | 1.6 km | 20 MW | 9.9 MW |
| Westburn Road | SP Energy Networks | 1.7 km | 26 MW | |
| Maukinfauld Road | SP Energy Networks | 1.9 km | 20 MW | |
| Whitlawburn | SP Energy Networks | 2.9 km | 22 MW | |
| Ashgrove Street | SP Energy Networks | 3.0 km | 23 MW | 8 MW |
Thinking of connecting near Clydesmill?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Clydesmill 275/33kV: 363 MW waiting
- Carntyne (SPD): 50 MW waiting
- Dalmarnock Storage BESS 132kV: 192 MW waiting
- DALMARNOCK 132/33KV SUBSTATION: 40 MW waiting
- Castlemilk 400kV: 300 MW waiting