DALMARNOCK 132/33KV SUBSTATION: grid connection queue
DALMARNOCK 132/33KV SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 40 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 23 Feb 2024 to 23 Feb 2024.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Dalmarnock Road BESS | DALMARNOCK BESS LTD | Battery storage | 40 | 23 Feb 2024 | n/a | Under Construction/Commissioning | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 7 Jul 2026 | Dalmarnock Road BESS | 30 Oct 2023 | 23 Feb 2024 | +4 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Ashgrove Street | SP Energy Networks | 0.7 km | 23 MW | 8 MW |
| Maukinfauld Road | SP Energy Networks | 1.1 km | 20 MW | |
| David Street | SP Energy Networks | 1.4 km | 22 MW | 10 MW |
| Eckford Street | SP Energy Networks | 2.1 km | 20 MW | 9.9 MW |
| Eastercraigs | SP Energy Networks | 2.3 km | 23 MW | 9.4 MW |
| Cambuslang | SP Energy Networks | 2.4 km | 18 MW |
Thinking of connecting near DALMARNOCK 132/33KV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Dalmarnock Storage BESS 132kV: 192 MW waiting
- Carntyne (SPD): 50 MW waiting
- Clydesmill 275/33kV: 363 MW waiting
- Clydesmill: 40 MW waiting
- Whitehill Bess 275/132kV: 500 MW waiting