Whitehill Bess 275/132kV: grid connection queue
Whitehill Bess 275/132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 1 Oct 2029 to 1 Oct 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| WHITEHILL BESS | GPC 1210 Ltd | Battery storage | 500 | 1 Oct 2029 | Medium | 1 Oct 2029 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Rottenrow | SP Energy Networks | 0.5 km | 25 MW | 6.3 MW |
| Rottenrow B | SP Energy Networks | 0.5 km | 4.6 MW | 16 MW |
| Hunter Street | SP Energy Networks | 0.6 km | 9.8 MW | |
| Virginia Street | SP Energy Networks | 0.9 km | 25 MW | 6.7 MW |
| Dundas Street | SP Energy Networks | 1.0 km | 14 MW | |
| Charles Street | SP Energy Networks | 1.1 km | 18 MW |
Thinking of connecting near Whitehill Bess 275/132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Elvanfoot 275/132/33kV: 250 MW waiting
- Finnieston: 60 MW waiting
- Dalmarnock Storage BESS 132kV: 192 MW waiting
- DALMARNOCK 132/33KV SUBSTATION: 40 MW waiting
- Carntyne (SPD): 50 MW waiting