Finnieston: grid connection queue
Finnieston GSP · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 60 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 17 Jul 2031 to 17 Jul 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| SEC 1 BESS | Bluestone Energy Ltd | Battery storage | 60 | 17 Jul 2031 | Medium | 17 Jul 2031 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Byres Road | SP Energy Networks | 0.7 km | 7.7 MW | |
| Grant Street | SP Energy Networks | 0.8 km | 27 MW | 9.4 MW |
| Old Dumbarton Road | SP Energy Networks | 0.9 km | 22 MW | 14 MW |
| St Vincent Crescent | SP Energy Networks | 1.0 km | 14 MW | 17 MW |
| Elliot Street | SP Energy Networks | 1.2 km | 13 MW | |
| Firhill Road | SP Energy Networks | 1.3 km | 23 MW | 13 MW |
Thinking of connecting near Finnieston?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Elvanfoot 275/132/33kV: 250 MW waiting
- Govan 132/33kV: 50 MW waiting
- Whitehill Bess 275/132kV: 500 MW waiting
- Partrick: 63 MW waiting
- Haggs Road: 40 MW waiting