Govan 132/33kV: grid connection queue

Govan 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 50 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 28 Jun 2028 to 28 Jun 2028.

1project in the queue
50 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
50 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Helen Street BESSVital Energi Solutions LimitedBattery storage5028 Jun 2028High28 Jun 2030Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Helen StreetSP Energy Networks0.2 km23 MW14 MW
CardonaldSP Energy Networks0.9 km12 MW
Elizabeth StreetSP Energy Networks1.2 km1.2 MW
LinthouseSP Energy Networks1.5 km1.6 MW
SecSP Energy Networks1.7 km33 MW28 MW
Old Dumbarton RoadSP Energy Networks2.1 km22 MW14 MW

Thinking of connecting near Govan 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points