Elvanfoot 275/132/33kV: grid connection queue

Elvanfoot 275/132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 250 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 31 Oct 2036 to 31 Oct 2036.

1project in the queue
250 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Ravengill Renewable Energy ParkRENEWCO POWER LIMITEDMixed and other25031 Oct 2036Low31 Oct 2036Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Grant StreetSP Energy Networks0.4 km27 MW9.4 MW
Elliot StreetSP Energy Networks0.6 km13 MW
West George StreetSP Energy Networks0.7 km24 MW9.9 MW
St Vincent CrescentSP Energy Networks0.8 km14 MW17 MW
Newton StreetSP Energy Networks1.1 km43 MW29 MW
Old Dumbarton RoadSP Energy Networks1.2 km22 MW14 MW

Thinking of connecting near Elvanfoot 275/132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.