Haggs Road: grid connection queue

Haggs Road GSP · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 40 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.

1project in the queue
40 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
KennisheadSTARLIGHT ENERGY UK LIMITEDBattery storage4031 Oct 2031Medium31 Oct 2031Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
LangsideSP Energy Networks0.6 km25 MW6.1 MW
NewlandsSP Energy Networks1.1 km23 MW13 MW
Haggs RoadSP Energy Networks1.1 km23 MW12 MW
Leslie StreetSP Energy Networks1.7 km24 MW8.8 MW
Carmunnock RoadSP Energy Networks1.9 km26 MW15 MW
Caledonia Bus DepotSP Energy Networks2.3 km34 MW25 MW

Thinking of connecting near Haggs Road?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points