Carntyne (SPD): grid connection queue
Carntyne (SPD) GSP · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Jun 2026 to 30 Jun 2026.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Provan Gas Works BESS | Vital Energi Solutions Limited | Battery storage | 50 | 30 Jun 2026 | n/a | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Eckford Street | SP Energy Networks | 0.4 km | 20 MW | 9.9 MW |
| Maukinfauld Road | SP Energy Networks | 0.7 km | 20 MW | |
| Frankfield | SP Energy Networks | 1.9 km | 14 MW | |
| Cambuslang | SP Energy Networks | 2.2 km | 18 MW | |
| Ashgrove Street | SP Energy Networks | 2.5 km | 23 MW | 8 MW |
| Consett Street | SP Energy Networks | 2.6 km | 25 MW | 6.3 MW |
Thinking of connecting near Carntyne (SPD)?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Clydesmill 275/33kV: 363 MW waiting
- Clydesmill: 40 MW waiting
- Dalmarnock Storage BESS 132kV: 192 MW waiting
- DALMARNOCK 132/33KV SUBSTATION: 40 MW waiting
- Whitehill Bess 275/132kV: 500 MW waiting