Busby 275kV: grid connection queue

Busby 275kV · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 150 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 17 Sep 2029 to 17 Sep 2029.

1project in the queue
150 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Westerton Lane BESSApatura Project 22 LtdBattery storage15017 Sep 2029Medium17 Sep 2029Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
ClarkstonSP Energy Networks1.3 km27 MW11 MW
CastleSP Energy Networks2.8 km2.6 MW2.5 MW
Berryhill RoadSP Energy Networks3.1 km23 MW12 MW
CastlemilkSP Energy Networks3.3 km20 MW15 MW
JacktonSP Energy Networks3.5 km22 MW19 MW
College MiltonSP Energy Networks3.8 km19 MW8.4 MW

Thinking of connecting near Busby 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points