Whitelee 275/33kV: grid connection queue
Whitelee 275/33kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 513 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 2 May 2031 to 2 May 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Whitelee | ScottishPower Renewables (UK) Limited | Onshore wind | 513 | 2 May 2031 | High | 18 Mar 2033 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Jackton | SP Energy Networks | 8.1 km | 22 MW | 19 MW |
| Westwood | SP Energy Networks | 9.0 km | 17 MW | |
| Newmilns | SP Energy Networks | 9.2 km | 16 MW | |
| Kelvin | SP Energy Networks | 10.1 km | 15 MW | |
| College Milton | SP Energy Networks | 10.4 km | 19 MW | 8.4 MW |
| Castle | SP Energy Networks | 10.8 km | 2.6 MW | 2.5 MW |
Thinking of connecting near Whitelee 275/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Whitelee Extension 275/33kV: 89 MW waiting
- Giffnock 275/33kV: 40 MW waiting
- East Kilbride B 275/33kV: 160 MW waiting
- East Kilbride 275kV: 200 MW waiting
- East Kilbride 275/33kV: 55 MW waiting