East Kilbride B 275/33kV: grid connection queue
East Kilbride B 275/33kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
3 projects with 160 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| AGS Nerston 2 BESS | Advance Grid Solutions Limited | Battery storage | 55 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
| AGS Nerston 3 BESS | Advance Grid Solutions Limited | Battery storage | 55 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
| AGS Nerston BESS | Advance Grid Solutions Limited | Battery storage | 50 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kelvin | SP Energy Networks | 1.3 km | 15 MW | |
| Westwood | SP Energy Networks | 2.4 km | 17 MW | |
| Common Farm | SP Energy Networks | 2.4 km | 15 MW | |
| Leonards Chapel | SP Energy Networks | 2.4 km | 17 MW | |
| Hunter | SP Energy Networks | 3.8 km | 25 MW | 16 MW |
| College Milton | SP Energy Networks | 3.9 km | 19 MW | 8.4 MW |
Thinking of connecting near East Kilbride B 275/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- East Kilbride 275kV: 200 MW waiting
- East Kilbride 275/33kV: 55 MW waiting
- Castlemilk 400kV: 300 MW waiting
- Strathaven 400kV: 800 MW waiting
- Strathaven 400/275kV: 500 MW waiting