Strathaven 400/275kV: grid connection queue
Strathaven 400/275kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 28 Oct 2033 to 28 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Devonhill | CBS ENERGY STORAGE ASSETS UK LIMITED | Battery storage | 500 | 28 Oct 2033 | Low | 28 Oct 2033 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Neilsland | SP Energy Networks | 0.7 km | 24 MW | 9.5 MW |
| Hamilton | SP Energy Networks | 1.9 km | 24 MW | 7 MW |
| Burnbank | SP Energy Networks | 2.2 km | 10 MW | |
| High Blantyre | SP Energy Networks | 2.9 km | 24 MW | 6.3 MW |
| Leven Street | SP Energy Networks | 4.9 km | 13 MW | 14 MW |
| Watling Street | SP Energy Networks | 5.4 km | 23 MW | 11 MW |
Thinking of connecting near Strathaven 400/275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Strathaven 400kV: 800 MW waiting
- Strathaven GSP 33kV: 50 MW waiting
- East Kilbride 275kV: 200 MW waiting
- East Kilbride 275/33kV: 55 MW waiting
- East Kilbride B 275/33kV: 160 MW waiting