Benzene

Strathaven GSP 33kV: grid connection queue

Strathaven GSP 33kV · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 50 MW is waiting to connect here (largest by capacity: solar). Contracted dates run from 31 Oct 2032 to 31 Oct 2032.

1project in the queue
50 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Crookedstone PVEnviromena Project Management UK LimitedSolar5031 Oct 2032Low31 Oct 2032Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
NeilslandSP Energy Networks0.7 km24 MW9.5 MW
HamiltonSP Energy Networks1.9 km24 MW7 MW
BurnbankSP Energy Networks2.2 km10 MW
High BlantyreSP Energy Networks2.9 km24 MW6.3 MW
Leven StreetSP Energy Networks4.9 km13 MW14 MW
Watling StreetSP Energy Networks5.4 km23 MW11 MW

Thinking of connecting near Strathaven GSP 33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points