Saltcoats 132/33kV: grid connection queue

Saltcoats 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026

2 projects with 130 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 21 Aug 2028 to 31 Oct 2029.

2projects in the queue
130 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
30 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Meiklelaught Farm BESSGPC 1127 LtdBattery storage3021 Aug 2028High21 Aug 2030Scopingnone
Saltcoats NEP BESS FacilityRashley New Energy LimitedBattery storage10031 Oct 2029Medium31 Oct 2029Awaiting Consentsnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Saltcoats MainSP Energy Networks1.5 km20 MW
StevenstonSP Energy Networks2.6 km11 MW7.5 MW
ByrehillSP Energy Networks4.8 km21 MW17 MW
RavensparkSP Energy Networks6.9 km13 MW
IrvineSP Energy Networks8.2 km24 MW4.1 MW
Dalrymple DriveSP Energy Networks8.7 km12 MW

Thinking of connecting near Saltcoats 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points