Hunterston East 400kV substation: grid connection queue

Hunterston East 400kV substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 10 Mar 2028 to 10 Mar 2028.

1project in the queue
200 MWwaiting to connect
0 MWalready connected
200 MWholding Gate 2
1date moves since 2 Jun 2026
200 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Hunterston Battery Storage FacilityHUNTERSTON GRID 1 LTDBattery storage20010 Mar 2028High10 Mar 2030Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
9 Jun 2026Hunterston Battery Storage Facility9 Mar 202610 Mar 2028+24 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Hunterston (Primary)SP Energy Networks0.3 km13 MW16 MW
FairlieSP Energy Networks5.1 km24 MW13 MW
LargsSP Energy Networks8.9 km16 MW
Bruchag PrimarySSEN Distribution9.2 km0 MW0 MW
Saltcoats MainSP Energy Networks10.4 km20 MW
StevenstonSP Energy Networks12.7 km11 MW7.5 MW

Thinking of connecting near Hunterston East 400kV substation?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points