Hunterston 400/132kV: grid connection queue

Hunterston 400/132kV · SP Transmission (southern Scotland) · register of 26 November 2026

3 projects with 325 MW are waiting to connect here (largest by capacity: battery storage, onshore wind + storage). Contracted dates run from 30 Apr 2033 to 31 Oct 2033.

3projects in the queue
325 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Hunterston Wind FarmGALILEO 01 LIMITEDOnshore wind + storage7030 Apr 2033Low30 Apr 2033Scoping1
Hunterston PARC BESSPULSE CLEAN ENERGY LIMITEDBattery storage25031 Oct 2033Low31 Oct 2033Scoping1
Hunterston HydrogenSTATKRAFT HYDROGEN UK HOLDING LIMITEDMixed and other531 Oct 2033Low31 Oct 2033Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Hunterston (Primary)SP Energy Networks0.3 km13 MW16 MW
FairlieSP Energy Networks5.1 km24 MW13 MW
LargsSP Energy Networks8.9 km16 MW
Bruchag PrimarySSEN Distribution9.2 km0 MW0 MW
Saltcoats MainSP Energy Networks10.4 km20 MW
StevenstonSP Energy Networks12.7 km11 MW7.5 MW

Thinking of connecting near Hunterston 400/132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.