Kilmarnock Town 275/33kV: grid connection queue

Kilmarnock Town 275/33kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 60 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 8 Feb 2027 to 8 Feb 2027.

1project in the queue
60 MWwaiting to connect
0 MWalready connected
60 MWholding Gate 2
1date moves since 2 Jun 2026
60 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Inchbean Energy ParkBROCKWELL STORAGE & SOLAR LIMITEDBattery storage608 Feb 2027High7 Feb 2029Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
23 Jun 2026Inchbean Energy Park30 Jun 20258 Feb 2027+19 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
StewartonSP Energy Networks2.5 km6.3 MW
Langlands StreetSP Energy Networks5.5 km23 MW11 MW
GrassyardsSP Energy Networks5.6 km11 MW
Queens DriveSP Energy Networks6.6 km15 MW
Kilmarnock MainSP Energy Networks7.1 km27 MW12 MW
RiversideSP Energy Networks9.7 km18 MW36 MW

Thinking of connecting near Kilmarnock Town 275/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points