Stalybridge 275kV: grid connection queue

Stalybridge 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 150 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Sep 2027 to 30 Sep 2027.

1project in the queue
150 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
150 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Zenobe Stalybridge ProjectZENOBE STALYBRIDGE LIMITEDBattery storage15030 Sep 2027High29 Sep 2029Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Primary substation 300913Electricity North West1.8 km31 MW8.5 MW
Primary substation 302311Electricity North West4.3 km15 MW0 MW
Bulk supply point 303021Electricity North West5.2 km31 MW26 MW
Primary substation 300061Electricity North West6.7 km32 MW6.1 MW
Primary substation 300711Electricity North West6.8 km18 MW9.4 MW
Primary substation 301326Electricity North West7.3 km6.1 MW0 MW

Thinking of connecting near Stalybridge 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points