Carrington 400KV: grid connection queue
Carrington 400KV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 2,130 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 8 May 2026 to 30 Oct 2038.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Cryogenic Battery System (Synchronous) | CRYOBATTERY ONE LIMITED | Battery storage | 50 | 8 May 2026 | n/a | Under Construction/Commissioning | none | |
| Carrington | CARRINGTON STORAGE LIMITED | Battery storage | 680 | 31 Oct 2027 | High | 30 Oct 2029 | Consents Approved | 2 |
| Trafford 2 BESS | FUTURE POINT MANCHESTER LIMITED | Battery storage | 1,400 | 30 Oct 2038 | Low | 30 Oct 2038 | Scoping | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 2 Jun 2026 | Carrington | 30 Oct 2026 | 31 Oct 2027 | +12 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Primary substation 100102 | Electricity North West | 1.4 km | 29 MW | 6.2 MW |
| Primary substation 100608 | Electricity North West | 2.4 km | 11 MW | 1.1 MW |
| Primary substation 100124 | Electricity North West | 2.7 km | 11 MW | 2 MW |
| Primary substation 100134 | Electricity North West | 2.9 km | 2.7 MW | 10 MW |
| Primary substation 100635 | Electricity North West | 3.3 km | 29 MW | 9.2 MW |
| Bulk supply point 100006 | Electricity North West | 3.6 km | 78 MW | 6.2 MW |
Thinking of connecting near Carrington 400KV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Carrington 275kV: 57 MW waiting
- Daines 400kV: 3,130 MW waiting
- Manchester South connection node A 400kv: 740 MW waiting
- Manchester South Connection Node B 400kV: 400 MW waiting
- Kearsley 275kV: 450 MW waiting