Carrington 275kV: grid connection queue
Carrington 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 57 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Carrington | PIVOTED POWER LLP | Battery storage | 57 | 31 Oct 2028 | High | 31 Oct 2030 | Awaiting Consents | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Primary substation 100102 | Electricity North West | 1.4 km | 29 MW | 6.2 MW |
| Primary substation 100608 | Electricity North West | 2.4 km | 11 MW | 1.1 MW |
| Primary substation 100124 | Electricity North West | 2.7 km | 11 MW | 2 MW |
| Primary substation 100134 | Electricity North West | 2.9 km | 2.7 MW | 10 MW |
| Primary substation 100635 | Electricity North West | 3.3 km | 29 MW | 9.2 MW |
| Bulk supply point 100006 | Electricity North West | 3.6 km | 78 MW | 6.2 MW |
Thinking of connecting near Carrington 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Carrington 400KV: 2,130 MW waiting
- Daines 400kV: 3,130 MW waiting
- Manchester South connection node A 400kv: 740 MW waiting
- Manchester South Connection Node B 400kV: 400 MW waiting
- Kearsley 275kV: 450 MW waiting