Manchester South Connection Node B 400kV: grid connection queue
Manchester South Connection Node B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 400 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Cellarhead PV & BESS Station | IB VOGT UK LTD | Solar + storage | 400 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Primary substation 100140 | Electricity North West | 0.3 km | 28 MW | 0 MW |
| Primary substation 100101 | Electricity North West | 1.1 km | 11 MW | 0 MW |
| Primary substation 100122 | Electricity North West | 1.2 km | 34 MW | 0 MW |
| Bulk supply point 100004 | Electricity North West | 1.4 km | 149 MW | 0 MW |
| Primary substation 100135 | Electricity North West | 1.6 km | 28 MW | 0 MW |
| Primary substation 100509 | Electricity North West | 1.6 km | 24 MW | 0 MW |
Thinking of connecting near Manchester South Connection Node B 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Carrington 400KV: 2,130 MW waiting
- Carrington 275kV: 57 MW waiting
- Middleton 400KV: 840 MW waiting
- Daines 400kV: 3,130 MW waiting
- Manchester South connection node A 400kv: 740 MW waiting