Manchester South Connection Node B 400kV: grid connection queue

Manchester South Connection Node B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 400 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.

1project in the queue
400 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Cellarhead PV & BESS StationIB VOGT UK LTDSolar + storage40030 Oct 2037Low30 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Primary substation 100140Electricity North West0.3 km28 MW0 MW
Primary substation 100101Electricity North West1.1 km11 MW0 MW
Primary substation 100122Electricity North West1.2 km34 MW0 MW
Bulk supply point 100004Electricity North West1.4 km149 MW0 MW
Primary substation 100135Electricity North West1.6 km28 MW0 MW
Primary substation 100509Electricity North West1.6 km24 MW0 MW

Thinking of connecting near Manchester South Connection Node B 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.