Middleton 400KV: grid connection queue
Middleton 400KV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 840 MW are waiting to connect here (largest by capacity: solar + storage, mixed and other). Contracted dates run from 30 Oct 2028 to 30 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Heysham Green Energy Centre | HEYSHAM GREEN NG LIMITED | Solar + storage | 400 | 30 Oct 2028 | High | 30 Oct 2030 | Awaiting Consents | none |
| Middleton BESS | Middleton Energy Storage Limited | Battery storage | 200 | 31 May 2029 | Medium | 31 May 2029 | Under Construction/Commissioning | 2 |
| Lightsource Middleton | Lightsource Renewable UK Development Limited | Mixed and other | 240 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 6 Oct 2026 | Middleton BESS | 30 Nov 2026 | 31 May 2029 | +30 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Primary substation 302855 | Electricity North West | 1.2 km | 31 MW | 4 MW |
| Primary substation 300015 | Electricity North West | 1.4 km | 26 MW | 3.4 MW |
| Bulk supply point 301101 | Electricity North West | 1.9 km | 47 MW | 4.2 MW |
| Primary substation 300004 | Electricity North West | 2.2 km | 32 MW | 4.2 MW |
| Primary substation 100614 | Electricity North West | 2.6 km | 30 MW | 11 MW |
| Primary substation 300029 | Electricity North West | 3.0 km | 25 MW | 4.2 MW |
Thinking of connecting near Middleton 400KV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Manchester South Connection Node B 400kV: 400 MW waiting
- Kearsley 275kV: 450 MW waiting
- Manchester South connection node A 400kv: 740 MW waiting
- Rochdale: 170 MW waiting
- Rochdale 275kV: 57 MW waiting