Kearsley 275kV: grid connection queue

Kearsley 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 450 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2028.

2projects in the queue
450 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
450 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Kearsley North Green Energy CentreKearsley North Green NG LimitedSolar + storage40031 Oct 2028High31 Oct 2030Scopingnone
KearsleyPIVOTED POWER LLPBattery storage5031 Oct 2028High31 Oct 2030Awaiting Consents1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Primary substation 200216Electricity North West0.5 km7 MW0 MW
Bulk supply point 200215Electricity North West1.1 km6.7 MW0 MW
Primary substation 200119Electricity North West2.2 km7 MW0 MW
Bulk supply point 200208Electricity North West3.1 km44 MW0 MW
Primary substation 200208 - No Heatmap ValuesElectricity North West3.1 km
Primary substation 205302Electricity North West3.2 km30 MW13 MW

Thinking of connecting near Kearsley 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points