Rochdale: grid connection queue
Rochdale GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 170 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Calderdale Wind Farm 240 MW | CALDERDALE WIND FARM LTD | Onshore wind | 170 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Primary substation 304887 | Electricity North West | 1.8 km | 10 MW | 5.2 MW |
| Primary substation 400093 | Electricity North West | 2.5 km | 30 MW | 9.9 MW |
| Primary substation 304886 | Electricity North West | 5.2 km | 30 MW | 8.8 MW |
| Bulk supply point 304882 | Electricity North West | 5.4 km | 83 MW | 46 MW |
| Primary substation 304894 | Electricity North West | 5.4 km | 29 MW | 13 MW |
| Primary substation 400092 | Electricity North West | 6.2 km | 29 MW | 7.9 MW |
Thinking of connecting near Rochdale?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Rochdale 275kV: 57 MW waiting
- Middleton 400KV: 840 MW waiting
- Elland 132kV: 100 MW waiting
- Kearsley 275kV: 450 MW waiting
- Leeds North Connection Node E 275kV: 249 MW waiting