Elland 132kV: grid connection queue

Elland 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 100 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2036 to 30 Oct 2036.

1project in the queue
100 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Elland BESSO&G Solar (SPV 39) LimitedBattery storage10030 Oct 2036Low30 Oct 2036Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Primary substation 303301Electricity North West13.5 km7 MW14 MW
Primary substation 304884Electricity North West14.3 km24 MW4 MW
Primary substation 304883Electricity North West15.9 km29 MW12 MW
Bulk supply point 304899Electricity North West16.2 km56 MW30 MW
Bulk supply point 304200Electricity North West16.6 km6.7 MW30 MW
Primary substation 300006Electricity North West17.4 km0 MW5.4 MW

Thinking of connecting near Elland 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points