Leeds North Connection Node E 275kV: grid connection queue

Leeds North Connection Node E 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 249 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.

1project in the queue
249 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Elland BESSPULSE CLEAN ENERGY LIMITEDBattery storage24931 Oct 2037Low31 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Primary substation 304884Electricity North West17.7 km24 MW4 MW
Primary substation 303301Electricity North West18.3 km7 MW14 MW
Bulk supply point 304899Electricity North West19.6 km56 MW30 MW
Primary substation 304883Electricity North West20.0 km29 MW12 MW

Thinking of connecting near Leeds North Connection Node E 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points