Leeds North Connection Node C 400kV: grid connection queue
Leeds North Connection Node C 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
5 projects with 2,430 MW are waiting to connect here (largest by capacity: battery storage, mixed and other). Contracted dates run from 30 Oct 2035 to 30 Oct 2035.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH) | TELIS ENERGY UK LIMITED | Mixed and other | 1,000 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
| FCC Thurcroft BESS | Downing Renewable Developments LLP | Battery storage | 750 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
| NEL Bluebell | SFEL Bluebell Limited | Battery storage | 240 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | none |
| NEL Springfield | UE 3 LTD | Battery storage | 240 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | none |
| West Melton PV & BESS Station | IBV WEST MELTON SOLAR PARK LIMITED | Solar + storage | 200 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 4 times: 3 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 3 Nov 2026 | FCC Thurcroft BESS | 31 Oct 2033 | 30 Oct 2035 | +24 months |
| 20 Oct 2026 | FCC Thurcroft BESS | 30 Oct 2035 | 31 Oct 2033 | -24 months |
| 13 Oct 2026 | West Melton PV & BESS Station | 31 Oct 2033 | 30 Oct 2035 | +24 months |
| 13 Oct 2026 | FCC Thurcroft BESS | 31 Oct 2033 | 30 Oct 2035 | +24 months |
Thinking of connecting near Leeds North Connection Node C 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Leeds North Connection Node E 132KV: 230 MW waiting
- Leeds North Connection Node D 400kV: 450 MW waiting
- Leeds North Connection Node G: 200 MW waiting
- Leeds South Connection Node B 132kV: 200 MW waiting
- Leeds North Connection Node C 132kV: 540 MW waiting