Leeds North Connection Node D 400kV: grid connection queue
Leeds North Connection Node D 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 450 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2035 to 31 Oct 2035.
2projects in the queue
450 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Tewitt Farm BESS | Apatura Battery Ltd | Battery storage | 200 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
| BlackDyke BESS | ANESCO LIMITED | Battery storage | 250 | 31 Oct 2035 | Low | 31 Oct 2035 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Leeds North Connection Node D 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Leeds South Connection Node B 132kV: 200 MW waiting
- Leeds North Connection Node G: 200 MW waiting
- Leeds North Connection Node A 400kV: 200 MW waiting
- Leeds North Connection Node C 132kV: 540 MW waiting
- Leeds North Connection Node C 400kV: 2,430 MW waiting