Leeds South Connection Node B 132kV: grid connection queue
Leeds South Connection Node B 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2039 to 30 Oct 2039.
1project in the queue
200 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Thurcroft Storage | BSR APPLICATIONS LIMITED | Battery storage | 200 | 30 Oct 2039 | Low | 30 Oct 2039 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Leeds South Connection Node B 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Leeds North Connection Node C 132kV: 540 MW waiting
- Leeds North Connection Node D 400kV: 450 MW waiting
- Leeds North Connection Node A 400kV: 200 MW waiting
- Leeds South Connection Node C 400kV: 410 MW waiting
- Leeds North Connection Node E 132KV: 230 MW waiting