Rugeley: grid connection queue
Rugeley GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2032 to 30 Oct 2032.
1project in the queue
50 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Rugeley | RUGELEY POWER GENERATION LIMITED | Battery storage | 50 | 30 Oct 2032 | Low | 30 Oct 2032 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Rugeley?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Rugeley 400kV: 600 MW waiting
- Staffordshire Connection Node B 132kV: 250 MW waiting
- Harlaston 400kV: 600 MW waiting
- Staffordshire Connection Node D 132kV: 300 MW waiting
- Bushbury 275kV: 480 MW waiting