Bushbury 275kV: grid connection queue
Bushbury 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 480 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2028 to 30 Oct 2028.
1project in the queue
480 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
480 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Bushbury Green Energy Centre | BUSHBURY GREEN NG LIMITED | Solar + storage | 480 | 30 Oct 2028 | High | 30 Oct 2030 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Bushbury 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Staffordshire Connection Node B 132kV: 250 MW waiting
- Staffordshire Connection Node D 132kV: 300 MW waiting
- Rugeley 400kV: 600 MW waiting
- Rugeley: 50 MW waiting
- Staffordshire Connection Node A 400kV: 2,760 MW waiting