Staffordshire Connection Node B 132kV: grid connection queue
Staffordshire Connection Node B 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 250 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Ebstree Road BESS | Voltwise Power Holdings Limited | Battery storage | 150 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
| Orchard BESS | RE Projects Development Limited | Battery storage | 100 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Orchard BESS | 31 Oct 2035 | 30 Oct 2037 | +24 months |
Thinking of connecting near Staffordshire Connection Node B 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bushbury 275kV: 480 MW waiting
- Staffordshire Connection Node D 132kV: 300 MW waiting
- Rugeley 400kV: 600 MW waiting
- Rugeley: 50 MW waiting
- Staffordshire Connection Node A 400kV: 2,760 MW waiting