Thurso South 275kV: grid connection queue

Thurso South 275kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

3 projects with 400 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2030 to 31 Oct 2034.

3projects in the queue
400 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Thurso South BESSWP Grid Storage 3 LimitedBattery storage10031 Oct 2030Medium31 Oct 2030Scoping1
Farm 100MW BESSApatura Battery LtdBattery storage10031 Oct 2033Low31 Oct 2033Scoping1
LythmoreQAIR SCOTLAND LIMITEDSolar + storage20031 Oct 2034Low31 Oct 2034Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Mount Pleasant PrimarySSEN Distribution1.1 km0 MW3.5 MW
Ormlie PrimarySSEN Distribution1.5 km0 MW9.9 MW
Thurso South GSPSSEN Distribution2.4 km
Forss PrimarySSEN Distribution9.2 km0 MW0.3 MW
Halkirk PrimarySSEN Distribution10.3 km0 MW0 MW
Dounreay GSPSSEN Distribution13.8 km

Thinking of connecting near Thurso South 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points