Banniskirk 400kV: grid connection queue
Banniskirk 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 3,258 MW are waiting to connect here (largest by capacity: offshore wind). Contracted dates run from 31 Dec 2029 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| OWPL Windfarm | OFFSHORE WIND POWER LIMITED | Offshore wind | 2,250 | 31 Dec 2029 | Medium | 31 Dec 2029 | Scoping | none |
| Ayre (ex Cluaran Ear - Thuath) Offshore Wind Farm | AYRE OFFSHORE WIND FARM LIMITED | Offshore wind | 1,008 | 31 Oct 2033 | Low | 31 Oct 2033 | Awaiting Consents | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Halkirk Primary | SSEN Distribution | 3.3 km | 0 MW | 0 MW |
| Mybster 2 GSP | SSEN Distribution | 5.7 km | ||
| Mybster 1 GSP | SSEN Distribution | 5.8 km | ||
| Thurso South GSP | SSEN Distribution | 9.6 km | ||
| Hastigrow Primary | SSEN Distribution | 10.6 km | 0 MW | 0 MW |
| Mount Pleasant Primary | SSEN Distribution | 11.0 km | 0 MW | 3.5 MW |
Thinking of connecting near Banniskirk 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- CAITHNESS ENERGY STORAGE 400KV SUBSTATION: 456 MW waiting
- Spittal 2 400kV: 1,000 MW waiting
- Spittal 400kV: 600 MW waiting
- Spittal 132kV: 462 MW waiting
- New Spittal 275kV: 200 MW waiting