Spittal 400kV: grid connection queue
Spittal 400kV · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 600 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| SSE Spittal Energy Park | SSE DE SOLAR HOLDCO LIMITED | Solar + storage | 600 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Mybster 2 GSP | SSEN Distribution | 3.9 km | ||
| Mybster 1 GSP | SSEN Distribution | 4.0 km | ||
| Halkirk Primary | SSEN Distribution | 11.0 km | 0 MW | 0 MW |
| Hastigrow Primary | SSEN Distribution | 12.5 km | 0 MW | 0 MW |
| Wick Primary | SSEN Distribution | 15.2 km | 0 MW | 5 MW |
| Latheron Primary | SSEN Distribution | 16.3 km | 0 MW | 1.1 MW |
Thinking of connecting near Spittal 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Spittal 2 400kV: 1,000 MW waiting
- Spittal 132kV: 462 MW waiting
- New Spittal 275kV: 200 MW waiting
- CAITHNESS ENERGY STORAGE 400KV SUBSTATION: 456 MW waiting
- Banniskirk 400kV: 3,258 MW waiting